| Project type | Hospitality installation |
|---|---|
| Location | River Oaks, Houston |
| Client type | Hotel |
| Challenge | A composition of upholstered panels and framed mirrors had to read as one piece across a wallcovered lounge wall above a long credenza, in a finished, furnished public space. |
| Scope | Layout marked and approved on the wall, twelve upholstered panels and six mirrors hung level and secured, protection of floors, furniture and wallcovering throughout |
| Crew size | One crew |
| Units installed | 18 pieces: 12 panels, 6 mirrors |
| Project duration | Not recorded |
| Work conditions | Finished, furnished public space |
| Result | Installed to the layout and photographed at handover |
| Related service | Hotel renovation installation · Hospitality |
Numbers are shown as recorded at handover; where a figure was not recorded it says so. Request project review for a project like this.

| Project type | Studio fit-out installation |
|---|---|
| Location | Houston |
| Client type | Dance studio |
| Challenge | A continuous mirror run across a long wall with windows opposite, seams aligned, plus barres mounted at a consistent height along the window wall. |
| Scope | Seven full-height mirror panels set, levelled and secured as one continuous wall; ballet barres mounted to blocking at one height along the window wall |
| Crew size | One crew |
| Units installed | 7 mirror panels, barre run |
| Project duration | Not recorded |
| Work conditions | Finished floor protected throughout |
| Result | Mirror wall seamless at eye height, barres level, photographed at handover |
| Related service | Commercial space turnover · Retail & office |
Numbers are shown as recorded at handover; where a figure was not recorded it says so. Request project review for a project like this.

| Project type | Office installation |
|---|---|
| Location | Bellaire, Houston |
| Client type | Corporate office |
| Challenge | Floor-to-ceiling glass on two sides of a boardroom needed sheer and blackout-grade drapery on ceiling track without touching the glazing, in a working office. |
| Scope | Ceiling track installed across the glass wall, sheer and drapery panels hung to the same height and return, TV wall left operational |
| Crew size | One crew |
| Units installed | Window wall, two elevations |
| Project duration | Not recorded |
| Work conditions | Occupied office, after-hours work |
| Result | Installed and photographed at handover |
| Related service | Commercial space turnover · Retail & office |
Numbers are shown as recorded at handover; where a figure was not recorded it says so. Request project review for a project like this.

| Project type | Studio fit-out installation |
|---|---|
| Location | Houston |
| Client type | Fitness studio |
| Challenge | Three tall framed mirrors had to be set at one height and spacing along a corridor wall with wood slat panelling and track lighting. |
| Scope | Three full-height framed mirrors hung level, spaced to the wall, secured for public use |
| Crew size | One crew |
| Units installed | 3 mirrors |
| Project duration | Not recorded |
| Work conditions | Finished space, polished floor protected |
| Result | Installed and photographed at handover |
| Related service | Commercial space turnover · Retail & office |
Numbers are shown as recorded at handover; where a figure was not recorded it says so. Request project review for a project like this.

| Project type | Office art installation |
|---|---|
| Location | Houston |
| Client type | Oil & gas company office |
| Challenge | Fourteen framed prints on glass across the office, including a five-piece run in the waiting room, hung to a layout in one working day. |
| Scope | Layout, hanging and securing of 14 framed prints on glass, 3×3 ft, across the office walls |
| Crew size | One crew |
| Units installed | 14 pieces |
| Project duration | One day, 30 September 2026 |
| Work conditions | Occupied office |
| Result | Completed on schedule, photo set delivered at handover |
| Related service | Construction closeout & punch list · Retail & office |
Numbers are shown as recorded at handover; where a figure was not recorded it says so. Request project review for a project like this.

| Project type | Residence / model-unit grade installation |
|---|---|
| Location | Houston high-rise |
| Client type | Private client |
| Challenge | A TV had to sit inside a four-part upholstered panel composition with cables hidden, next to an oversized framed canvas, on a wall shared with floor-to-ceiling glass. |
| Scope | Upholstered panels mounted around a recessed TV, cabling concealed, oversized framed art hung and secured |
| Crew size | One crew |
| Units installed | 4 panels, 1 TV, 1 artwork |
| Project duration | Not recorded |
| Work conditions | Occupied residence |
| Result | Installed and photographed at handover |
| Related service | Property managers: model units and amenity spaces · Retail & office |
Numbers are shown as recorded at handover; where a figure was not recorded it says so. Request project review for a project like this.

| Project type | Office art installation |
|---|---|
| Location | Downtown Houston |
| Client type | Law office |
| Challenge | Certificates and art had to form one gallery wall in a waiting room, approved before any drilling. |
| Scope | Gallery wall laid out on the floor, approved, then hung level and secured |
| Crew size | One crew |
| Units installed | Not recorded |
| Project duration | Not recorded |
| Work conditions | Occupied office |
| Result | Layout approved before drilling, installed in one visit, photographed at handover |
| Related service | Construction closeout & punch list · Retail & office |
Numbers are shown as recorded at handover; where a figure was not recorded it says so. Request project review for a project like this.

| Project type | Office art installation |
|---|---|
| Location | Houston |
| Client type | Corporate office |
| Challenge | A triptych aligned across a hallway wall, plus a high-wall flag installation on a ladder in the same office program. |
| Scope | Three-panel art installation aligned and secured; high-wall flag installation |
| Crew size | One crew |
| Units installed | Not recorded |
| Project duration | Not recorded |
| Work conditions | Occupied office |
| Result | Installed in one visit, photographed at handover |
| Related service | Construction closeout & punch list · Retail & office |
Numbers are shown as recorded at handover; where a figure was not recorded it says so. Request project review for a project like this.
Property-scale cases (hotel blocks, warehouse resets, closeouts) get their own page under /commercial/projects/ as they close.
Because it only holds jobs we installed, with recorded numbers. Projections and example projects are not on this page.
Yes, with the client's permission, for the projects listed here and for residential work on request.
Yes. A photo set at handover is part of every engagement and goes to your file.
Request project review
Your name, a way to reach you, and what has to be done. Attach the punch list, plans, finish schedule or photos: PDF, Excel, Word or images.
Prefer text? Send the photos to
(737) 361-9111
Insured by Progressive · Certificate of insurance and policy number on request